Name: Acquisition of 110 MW Dnipro Buzska Wind Farm Project
Project Director: Liliya Surzhenko
Senior Strategy Expert: Yuri Kubrushko
Senior Legal Expert: Oleg Dovzhenko
Client: Greenworx
Funding source: Greenworx
Duration: 2017-2018
Description: due diligence of 110 MW wind power plant construction project, assisting in acquisition of the majority stake in the SPV
Tasks/activities performed:
- legal, regulatory, technical and environmental due diligence
- identification of risks, developing mitigation strategies
- drafting of the Share Purchase Agreement, supporting transaction on purchase of the majority stake in the SPV
- support to negotiations with TSO and Oblenergo to conclude grid connection agreement
- advising on legal and regulatory issues related to electricity market operations in Ukraine.